Category: Latest News Items …

  • Lower Main Street Upgrade – Week 5

    During the fifth week of the lower Main Street upgrade work has been progressing on the other side of the street. The large concrete structure in the middle of the road where the workmen are is the water main that was responsible for the large camber in the original road surface.

  • The Square Upgrade – Week 4

    Work in The Square is complete apart from a few remaining small jobs such as finishing the light fittings and planting the tree. The footpath alongside 1st Presbyterian Church. The granite nidger bands are in place at either end of The Square. The circular seat has been returned and the square hole to the right awaits its tree.  […]

  • Community Litter Pick – 6th September

    There will be another Community Litter Pick on Saturday 6th September.  Everyone is welcome to come along and help clean up our village! Dayglo jackets, protective gloves and litter pick tools will be provided. Date: Saturday 6th September Time: 1:00 pm to 3:00 pm Meeting point: Car Park in front of 2nd Saintfield Presbyterian Church. […]

  • Shop Local, Shop Saintfield!

    Our traders and businesses need your support more than ever during the disruptive roadworks on Main Street. Please shop locally and help them through this difficult period.

  • Lower Main Street Upgrade – Week 4

    At the end of the fourth week the kerbs and gutters are in place, and resurfacing has begun on the first half of lower Main Street. It looks much better already!

  • The Square Upgrade – Week 3

    Work has progressed well in The Square and great changes can be seen at the end of the third week.  The Square has been resurfaced and the granite pavements, kerbs and gutters are in place. In order to better define the limits of The Square bricks have been laid into the road surface at both ends […]

  • Log Art At Rowallane!

    Below is a photograph of some log art that has appeared recently in Rowallane. The bandstand that used to be on the promenade in Newcastle can be seen in the background.

  • Well Done Saintfield High School Pupils!

    Well done to all of the Saintfield High School pupils who have achieved good grades in their exams!

  • The Square Upgrade – Week 2

    Work is progressing well with the upgrade of The Square.  At the end of the second week the pavement is taking shape beside the Guildhall of 1st Presbyterian Church. The round hole in the photograph below is where the large circular seat/planter/sign was located. As can be seen, provision has been made for access to businesses.

  • Lower Main Street Upgrade – Week 3

    At the end of the third week there were three excavating machines working on lower Main Street.  The road has been lowered to remove the camber which had built up over the years by the addition of several top surfaces, and all the underground services have to be lowered accordingly. The severity of the camber […]