The works have been scheduled for this period when schools are closed and there is typically less traffic commuting on this route. Whilst this work is largely outside the main street and town centre (completed in 2019), there will be some disruption experienced and steps will be taken to minimise the impact.
Click on the map below to download the pdf version which outlines the scheduled activity over the 12 weeks required for completion of the works. With the exception of a short closure of Windmill Road at the beginning of the works, the remaining works are to be undertaken under lane closure with temporary traffic lights. The programme of works will operate near critical junctions at times and to ensure a steady flow of traffic these will be manned Monday to Friday from 7am to 7pm and at busy times over the weekends by a specialist traffic management company.
Real time updates on the works as they progress will be available at: www.phoenixnaturalgas.com/projects
Leave A Comment