Kerbing and drainage works will carry on through the week. Men will work an average minimum of 10hrs per day this week.
On Wednesday 3rd a mini spreader will be on site to infill the section between the newly laid surface and the water mains, this will enable barriers to be adjusted to provide parking on one side of the street.
On Friday 5th a spreader will again be onsite completing the remainder of the road base.
On Saturday 6th works will commence on the footway. During this time pedestrians will be diverted onto the new surface and thus around the works.
These footway works are planned for completion on Friday 12th when another layer of black top will be laid on the carriageway before traffic is transferred on to it and works start on the opposite footway.
If anyone has any deliveries larger than normal planned for next week please let the supervisor know and hopefully off loading can be accommodated.